May 29th

Got back from Brisbane today and saw the carpenter on site doing all the doors including the pivot front door and trifold doors at the back of the property. The stairs are in and look great. The site supervisor said it could be 6.5wks before IOC. Exciting! Can’t wait.ImageImageImageImage

May 19th

Big couple of weeks. Clarendon now trying to minimise the delay in completion. Estimated 5wks over contract. Gyprock completed in 3 days, cabling in, insulation in, electrical in, down pipes in, sewer and gas connections done. Next carpentry – cornices, skirting and sanding. Bulkhead in kitchen not correct. It has no nook so they will have to pull frame and gyprock apart to redesign unfortunately.