Month: May 2014
May 29th
May 19th
Big couple of weeks. Clarendon now trying to minimise the delay in completion. Estimated 5wks over contract. Gyprock completed in 3 days, cabling in, insulation in, electrical in, down pipes in, sewer and gas connections done. Next carpentry – cornices, skirting and sanding. Bulkhead in kitchen not correct. It has no nook so they will have to pull frame and gyprock apart to redesign unfortunately.
May 9th
Move in update …… 10 weeks from 16th May, bringing us to beginning of August at the earliest for a moving date. If we start the pool end August we are looking at end November before we can use the pool which means it will be ready for Christmas.